500kg natural gas hydrogen production unit

Short Description:

The natural gas outside the battery limit is first pressurized to 1.6Mpa by the compressor, then heated to about 380 ℃ by the feed gas preheater in the convection section of the steam reformer, and enters the desulfurizer to remove the sulfur in the feed gas below 0.1ppm.


Product Detail

 

Technological process

 

Natural gas compression and conversion

 

The natural gas outside the battery limit is first pressurized to 1.6Mpa by the compressor, then heated to about 380 ℃ by the feed gas preheater in the convection section of the steam reformer furnace, and enters the desulfurizer to remove the sulfur in the feed gas below 0.1ppm. The desulfurized feed gas and process steam (3.0mpaa) Adjust the mixed gas preheater according to the automatic value of H2O / ∑ C = 3 ~ 4, further preheat to more than 510 ℃, and evenly enter the conversion pipe from the upper gas gathering main pipe and upper pigtail pipe. In the catalyst layer, methane reacts with steam to generate CO and H2. The heat required for methane conversion is provided by the fuel mixture burned at the bottom burner. The temperature of the converted gas out of the reformer furnace is 850 ℃, and the high temperature is converted to high temperature。 The chemical gas enters the tube side of the waste heat boiler to produce 3.0mpaa saturated steam. The temperature of the conversion gas from the waste heat boiler drops to 300 ℃, and then the conversion gas enters the boiler feed water preheater, conversion gas water cooler and conversion gas water separator in turn to separate the condensate from the process condensate, and the process gas is sent to the PSA.

 

The natural gas as fuel is mixed with the pressure swing adsorption desorption gas, and then the fuel gas volume into the fuel gas preheater is adjusted according to the gas temperature at the outlet of the reformer furnace. After flow adjustment, the fuel gas enters the top burner for combustion to provide heat to the reformer furnace.

 

The desalted water is preheated by the desalted water preheater and boiler feed water preheater and enters the by-product steam of flue gas waste boiler and reforming gas waste boiler.

 

In order to make the boiler feed water meet the requirements, a small amount of phosphate solution and deoxidizer shall be added to improve the scaling and corrosion of boiler water. The drum shall continuously discharge part of boiler water to control the total dissolved solids of boiler water in the drum.

 

Pressure swing adsorption

 

PSA consists of five adsorption towers. One adsorption tower is in adsorption state at any time. The components such as methane, carbon dioxide and carbon monoxide in the conversion gas stay on the surface of the adsorbent. Hydrogen is collected from the top of the adsorption tower as non-adsorption components and sent out of the boundary. The adsorbent saturated by impurity components is desorbed from the adsorbent through the regeneration step. After being collected, it is sent to the reformer furnace as fuel. The regeneration steps of the adsorption tower are composed of 12 steps: first uniform drop, second uniform drop, third uniform drop, forward discharge, reverse discharge, flushing, third uniform rise, second uniform rise, first uniform rise and final rise. After regeneration, the adsorption tower is again capable of treating converted gas and producing hydrogen. The five adsorption towers take turns to carry out the above steps to ensure continuous treatment. The purpose of converting gas and continuously producing hydrogen at the same time.

 

Main process equipment

 

S/N Equipment

name

Main

specifications

Main materials Unit weight ton QTY Remarks
Natural gas steam conversion section          
1 Reformer furnace       1 set  
  Thermal load Radiation section: 0.6mW        
    Convection section: 0.4mw        
  Burner Heat load: 1.5mw/set compound material   1  
  High temperature reformer tube   HP-Nb      
  Upper pigtail   304SS   1 set  
  Lower pigtail   Incoloy   1 set  
  Convection section heat exchanger          
    Preheating of mixed raw materials 304SS   1 group  
    Feed gas preheating 15CrMo   1 group  
    Flue gas waste boiler 15CrMo   1 group  
  Manifold   Incoloy   1 group  
2 Chimney DN300 H=7000 20#   1  
    Design temperature: 300 ℃        
    Design pressure: ambient pressure        
3 Desulfurization tower Φ400 H=2000 15CrMo   1  
    Design temperature: 400 ℃        
    Design pressure: 2.0MPa        
4 Conversion gas waste boiler Φ200/Φ400 H=3000 15CrMo   1  
    Design temperature: 900 ℃ / 300 ℃        
    Design pressure: 2.0MPa        
    Heat load: 0.3mw        
    Hot side: high temperature conversion gas        
    Cold side: boiler water        
5 Boiler feed pump Q=1m3/h 1Cr13   2 1+1
    Design temperature: 80 ℃        
    Inlet pressure: 0.01Mpa        
    Outlet pressure: 3.0MPa        
    Explosion proof motor: 5.5kw        
6 Boiler feed water preheater Q=0.15MW 304SS/20R   1 Hairpin
    Design temperature: 300 ℃        
    Design pressure: 2.0MPa        
    Hot side: conversion gas        
    Cold side: desalted water        
7 Reforming gas water cooler Q=0.15MW 304SS/20R   1  
    Design temperature: 180 ℃        
    Design pressure: 2.0MPa        
    Hot side: conversion gas        
    Cold side: circulating cooling water        
8 Reforming gas water separator Φ300 H=1300 16MnR   1  
    Design temperature: 80 ℃        
    Design pressure: 2.0MPa        
    Demister: 304SS        
9 Dosing System phosphate Q235   1 set  
    Deoxidizer        
10 Desalination tank Φ1200 H=1200 Q235   1  
    Design temperature: 80 ℃        
    Design pressure: ambient pressure        
11 Natural gas compressor Exhaust volume: 220m3 / h        
    Suction pressure: 0.02mpag        
    Exhaust pressure: 1.7mpag        
    Oil free lubrication        
    Explosion proof motor        
    Motor power: 30KW        
12 Natural gas buffer tank Φ300 H=1000 16MnR   1  
    Design temperature: 80 ℃        
    Design pressure: 0.6MPa        
PSA part          
1 Adsorption tower DN700 H=4000 16MnR   5  
    Design temperature: 80 ℃        
    Design pressure: 2.0MPa        
             
2 Desorption gas buffer tank DN2200 H=10000 20R   1  
    Design temperature: 80 ℃        
    Design pressure: 0.2MPa        

001